Project Phases
View all tasksPool pipe replacement and drainage run in trenches. Spec changed from original quote — upgraded pipes installed.
Level the terrace floor ready for resin application.
Level and prepare pool internal walls before coping and tile band.
Fit coping stones around pool perimeter. Changed from original edging tile spec.
Fit waterline tile band inside pool. Colour and height TBC.
Render and paint surrounding walls. Run parallel with pool prep.
Prepare pool shell surface and apply new fibreglass lining (3 layers polyester resin + epoxy).
Apply EcoFinish aquaBRIGHT — French Grey (AB3-FG). Product in stock.
Apply resin aggregate finish to terrace floor. Resin ordered — expected end of March 2026.
Miscellaneous additional works including electrical, plumbing, shower, gate, and chimney.
Latest Updates
View allProject tracker set up. Here is a summary of where we are: ✅ Pool pipework complete (spec upgraded). ✅ Coping stones ordered — estimated delivery ~2 weeks. ✅ EcoFinish French Grey powder in stock. 🔄 Floor levelling in progress. ⏳ Terrace resin ordered — expected end of March 2026. Next steps: level floor, level pool walls, fit coping stones, agree tile band colour and height, then pool prep and refibre. 3D scan of current site: https://poly.cam/capture/1570EA11-E612-4CD5-9D57-508E06537788
Canary Detect — 20/02/2026