Crusty's Pool Refurb

Project Timeline

A record of key milestones, completed tasks, and site updates as the project progresses.

Task Complete29 March 2026

Coping Stones Fitted

Coping stones delivered and fitted around pool perimeter. Coping Stones phase complete.

Milestone28 March 2026

Coping Stones Measured and Ordered

Coping stones measured, spec confirmed and order placed. Quote S00973-C (replaces original edging tile spec).

Task Complete27 March 2026

Hollow Concrete Repair Complete

Hollow and damaged sections of terrace concrete broken out and replaced with new concrete. ADD-009, price TBC.

Task Complete27 March 2026

Drain Pipes Capped

Small drain pipes from top to bottom terrace capped off. Groundworks tidy-up complete.

Task Complete24 March 2026

First Coat Render Applied to Garden Walls

First coat of render applied to garden walls surrounding pool area. Final coat to follow once cured.

Task Complete24 March 2026

Terrace Floor Levelling Complete

Terrace floor levelled and ready for resin finish. Floor Levelling phase complete.

Task Complete24 March 2026

Channel Dug — Pump Room to Heater

Channel dug from pump room to heater enclosure. Services installation (drainage, water, electrical duct) in progress.

Milestone13 March 2026

Payment — Tile Band Materials (ADD-001)

€2,000 paid for tile band tiles and epoxy adhesive. Materials only — labour included in original quote.

Task Complete12 March 2026

Bottom Terrace Step Trimmed

Bottom terrace step trimmed down to correct height. Part of terrace step tiles rework (ADD-008).

Decision Made27 February 2026

Tile Band Height Decided — 38mm

Tile band height confirmed at 38mm (above pool jets). Decision resolved.

Decision Made27 February 2026

Tile Band Colour Agreed

Customer agreed tile band colour. Decision resolved.

Milestone11 February 2026

Payment — Terrace (S01227)

€8,000 deposit paid on terrace quote S01227 (Pebbletone/Resin Alpine Granite finish).

Milestone20 December 2025

Solar Shower Cancelled

Decision made to cancel the solar shower installation. Quote S01227-E marked as superseded.

Task Complete15 December 2025

Pool Pipes Replaced

Old pool pipework removed and replaced with upgraded spec. Groundworks phase progressing.

Milestone2 December 2025

Payment — Pool Pipework (S01342)

€5,307.20 paid (80% of S01342). Pool pipework replacement underway.

Milestone25 September 2025

Project Started

Pool and terrace refurbishment project officially started with Canary Detect.

Milestone25 September 2025

Deposit Paid — Pool Recoating (S00973)

€9,448 deposit paid. Covers EcoFinish pool interior, fibreglass refibre and coping stones.